Naval Post Graduate School, Monterey, California
Cost: $2.6 Million
Duration: Four (4) Months
Installed Modules: 868
Status: Completed
This project was awarded to Stronghold Engineering, Inc. through a competitive price / best value selection process. Stronghold’s proposal was determined to provide the Navy and its client, the Naval Post Graduate School, the best overall value in terms of quality of the system and high expected generation output. This grid tied, fast-track, design build, photovoltaic installation project required significant coordination to address the conditions of the roof and the occupied facilities below. Stronghold worked hand in hand with the school’s local staff to ensure the installation of this 187kW system did not affect the schools primary focus – education.
What They Say…
“This contractor was very efficient and organized. They were very responsive to all our needs.”